Placing dumped riprap for the bridge structures.
Placing dumped riprap for the bridge structures. Dumped riprap placement is currently underway for the bridge structures (see attached photos).
Precast planks are also in production, with the final casting anticipated for mid-December.
Bridge deck activities are expected to begin in mid-January 2026.