Placing dumped riprap for the bridge structures.

Placing dumped riprap for the bridge structures. Dumped riprap placement is currently underway for the bridge structures (see attached photos).

Precast planks are also in production, with the final casting anticipated for mid-December.

Bridge deck activities are expected to begin in mid-January 2026.

Blind Renaissance
Since 1972, Blind Renaissance has an extensive history of creating the strong visual identity and cohesive media presence demanded by the sophistication of marketing environments. We design engaging, client-specific promotional materials by combining an educated artistic sensibility, knowledge of advertising trends in multiple industries and the ability to appropriately utilize new design, web and printing technology.
http://www.icblind.com
Previous
Previous

Grading work and riprap placement within the stream bed have been completed.

Next
Next

Completion of Wingwall #2, Wingwall #4 and center pier.