Estimated Project Milestones
Start Bridge Construction - February 2025
Substantial Completion - June 2026
Project Schedule
June Updates
Work for drilled shaft No. 10 has already begun.
Simultaneously, an excavation for abutment wall No. 1 along the Haleiwa side (left of pier) underway. Reference this work in the picture below. Before proceeding with the abutment wall, the concrete overpour for the drilled shafts (the two shafts seen in this picture) will be chipped away.
12 drilled shafts have been completed to date. Drilled shaft production is still ongoing.
Started construction on abutment and wing walls along Haleiwa side (left of pier).
Construction for the electrical has begun. This work is for the streetlights and communication lines.





May 2025 Updates
Drilled Shaft Production Began Monday 5/5 on Haleiwa Side of Project.. Five drilled shafts have been successfully completed
May 2025 Updates
Project waiting for approval to proceed with production drilled shafts for the future bridge construction.
April 2025 Updates
Load Test Shaft concrete pour was completed on 3/17/25
Coral Import is complete.