Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

August Schedule

Work for abutment and wingwall on the right side of the pier, going towards Waimea just started.

Read More
Blind Renaissance Blind Renaissance

July

Construction began for the abutment wall and wing walls on the right side of the pier, along Waimea.

Construction of abutment wall and wing walls on left side of the pier, along Haleiwa moves forward.

Read More
Blind Renaissance Blind Renaissance

June Updates

  • Work for drilled shaft No. 10 has already begun.

  • Simultaneously, an excavation for abutment wall No. 1 along the Haleiwa side (left of pier) underway. Reference this work in the picture below. Before proceeding with the abutment wall, the concrete overpour for the drilled shafts (the two shafts seen in this picture) will be chipped away.

  • 12 drilled shafts have been completed to date. Drilled shaft production is still ongoing.

  • Started construction on abutment and wing walls along Haleiwa side (left of pier).

  • Construction for the electrical has begun. This work is for the streetlights and communication lines.

Read More