Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

June Updates

  • Work for drilled shaft No. 10 has already begun.

  • Simultaneously, an excavation for abutment wall No. 1 along the Haleiwa side (left of pier) underway. Reference this work in the picture below. Before proceeding with the abutment wall, the concrete overpour for the drilled shafts (the two shafts seen in this picture) will be chipped away.

  • 12 drilled shafts have been completed to date. Drilled shaft production is still ongoing.

  • Started construction on abutment and wing walls along Haleiwa side (left of pier).

  • Construction for the electrical has begun. This work is for the streetlights and communication lines.

Read More
Blind Renaissance Blind Renaissance

May 2025 Updates

Drilled Shaft Production Began Monday 5/5 on Haleiwa Side of Project.. Five drilled shafts have been successfully completed

Read More
Blind Renaissance Blind Renaissance

May 2025 Updates

Project waiting for approval to proceed with production drilled shafts for the future bridge construction.

Read More
Blind Renaissance Blind Renaissance

April 2025 Updates

Load Test Shaft concrete pour was completed on 3/17/25

Coral Import is complete.

Read More