Estimated Project Milestones
Start Bridge Construction - February 2025
Substantial Completion - June 2026
Project Schedule
February 2026
We’re continuing work on the bridge deck today, including forming and placing the rebar.
Bridge pour still projected for the end of February.
January 2026
Work remains in progress as crews continue to advance the CLSM backfill.
Next week's operations will include setting the precast planks and commencing bridge deck construction.
Precast planks have been placed and are now beginning to work on the bridge deck.
November 2025
Dumped riprap placement is currently underway for the bridge structures (see attached photos).
Precast planks are also in production, with the final casting anticipated for mid-December.
Bridge deck activities are expected to begin in mid-January 2026.
Grading work and riprap placement within the stream bed have been completed.