Completion Scheduled for November 2027 Estimated Project Milestones Start Bridge Construction - February 2025 Substantial Completion - June 2026 Project Schedule Blind Renaissance 9/1/26 Blind Renaissance 9/1/26 September Read More Blind Renaissance 8/1/26 Blind Renaissance 8/1/26 August No active work occurred this period and no tasks are scheduled for the next two weeks. Read More Blind Renaissance 7/1/26 Blind Renaissance 7/1/26 July July operations focus on grinding and grooving.Crews have completed the grinding and grooving of the bridge—please see the attached photo for reference. Read More Blind Renaissance 5/22/26 Blind Renaissance 5/22/26 June Read More Older Posts
Blind Renaissance 8/1/26 Blind Renaissance 8/1/26 August No active work occurred this period and no tasks are scheduled for the next two weeks. Read More
Blind Renaissance 7/1/26 Blind Renaissance 7/1/26 July July operations focus on grinding and grooving.Crews have completed the grinding and grooving of the bridge—please see the attached photo for reference. Read More