Estimated Project Milestones
Start Bridge Construction - February 2025
Substantial Completion - June 2026
Project Schedule
November 2025
Dumped riprap placement is currently underway for the bridge structures (see attached photos).
Precast planks are also in production, with the final casting anticipated for mid-December.
Bridge deck activities are expected to begin in mid-January 2026.
Grading work and riprap placement within the stream bed have been completed.