Estimated Project Milestones
Start Bridge Construction - February 2025
Substantial Completion - June 2026
Project Schedule
May
Approach slabs are scheduled to be poured second week on May
Following up on our May 1 update, the project remains right on schedule. The approach slabs were successfully poured last week as planned (see attached photos for reference).
Upcoming Schedule:
Stripping approach slab forms
Erecting forms and placing rebar for the end posts
Pouring the end posts
Stripping forms for the end posts
April 2026
Pouring the sleeper slabs, bridge railings, and utility beams.
April 15: Pouring continuing
February 2026
We’re continuing work on the bridge deck today, including forming and placing the rebar.
Bridge pour still projected for the end of February.