Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

February 2026

We’re continuing work on the bridge deck today, including forming and placing the rebar.

Bridge pour still projected for the end of February.

Read More
Blind Renaissance Blind Renaissance

January 2026

Work remains in progress as crews continue to advance the CLSM backfill.

Next week's operations will include setting the precast planks and commencing bridge deck construction.

Precast planks have been placed and are now beginning to work on the bridge deck.

Read More
Blind Renaissance Blind Renaissance

December

Backfilling of the abutments and wingwalls has commenced. This will continue for the month of December.

Backfilling of the abutments and wingwalls using on-site mixed CLSM will continue through December.

There will be on break from December 24, 2025 and returning January 5, 2026.

Read More
Blind Renaissance Blind Renaissance

November 2025

Dumped riprap placement is currently underway for the bridge structures (see attached photos).

Precast planks are also in production, with the final casting anticipated for mid-December.

Bridge deck activities are expected to begin in mid-January 2026.

Grading work and riprap placement within the stream bed have been completed.