Estimated Project Milestones
Start Bridge Construction - February 2025
Substantial Completion - June 2026
Project Schedule
August Schedule
Work for abutment and wingwall on the right side of the pier, going towards Waimea just started.
June Updates
Work for drilled shaft No. 10 has already begun.
Simultaneously, an excavation for abutment wall No. 1 along the Haleiwa side (left of pier) underway. Reference this work in the picture below. Before proceeding with the abutment wall, the concrete overpour for the drilled shafts (the two shafts seen in this picture) will be chipped away.
12 drilled shafts have been completed to date. Drilled shaft production is still ongoing.
Started construction on abutment and wing walls along Haleiwa side (left of pier).
Construction for the electrical has begun. This work is for the streetlights and communication lines.




