Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

April 2026

Pouring the sleeper slabs, bridge railings, and utility beams.

Read More
Blind Renaissance Blind Renaissance

March 2026

Bridge paving conducted in February was a resounding success.

Read More
Blind Renaissance Blind Renaissance

February 2026

We’re continuing work on the bridge deck today, including forming and placing the rebar.

Bridge pour still projected for the end of February.

Read More
Blind Renaissance Blind Renaissance

January 2026

Work remains in progress as crews continue to advance the CLSM backfill.

Next week's operations will include setting the precast planks and commencing bridge deck construction.

Precast planks have been placed and are now beginning to work on the bridge deck.

Read More