Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

July

July operations focus on grinding and grooving.
Crews have completed the grinding and grooving of the bridge—please see the attached photo for reference.

Read More
Blind Renaissance Blind Renaissance

May

Approach slabs are scheduled to be poured second week on May

Following up on our May 1 update, the project remains right on schedule. The approach slabs were successfully poured last week as planned (see attached photos for reference).

Upcoming Schedule:

  • Stripping approach slab forms

  • Erecting forms and placing rebar for the end posts

  • Pouring the end posts

  • Stripping forms for the end posts

Read More
Blind Renaissance Blind Renaissance

April 2026

Pouring the sleeper slabs, bridge railings, and utility beams.

April 15: Pouring continuing