Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

December

Backfilling of the abutments and wingwalls has commenced. This will continue for the month of December.

Backfilling of the abutments and wingwalls using on-site mixed CLSM will continue through December.

There will be on break from December 24, 2025 and returning January 5, 2026.

Read More
Blind Renaissance Blind Renaissance

November 2025

Dumped riprap placement is currently underway for the bridge structures (see attached photos).

Precast planks are also in production, with the final casting anticipated for mid-December.

Bridge deck activities are expected to begin in mid-January 2026.

Grading work and riprap placement within the stream bed have been completed.

Read More
Blind Renaissance Blind Renaissance

October 2025

Preparing to pour Wingwall #2, Wingwall #4 and Pier Wall.

Read More
Blind Renaissance Blind Renaissance

September 2025

Construction for center of pier begins.

Read More