Work Progress
Concrete Poured for Abutment Wall and Wingwall Shaft Caps, Left Side of Pier
Concrete was poured for the abutment wall and wingwall shaft caps along the left side of the pier.
Construction of abutment and wingwalls along right side of pier is still ongoing
Mid September updates
Haleiwa and Waimea Construction Continuing
Construction for the abutment walls and wing walls along both Haleiwa and Waimea side of the pier is continuing.
Abutment Walls and Wing Walls Ongoing
Construction work for the abutment walls and wing walls along Haleiwa side and Waimea side of the pier is ongoing.
Bridge abutments and wingwalls
Bridge abutments and wingwalls are still currently under construction, with a focus on the left side of the pier.
Abutment wall and wing walls on left side of the pier, along Haleiwa moves forward.
Construction of abutment wall and wing walls on left side of the pier, along Haleiwa is moving forward.
Abutment wall and wing walls on the right side of the pier, along Waimea begins.
Construction began for the abutment wall and wing walls on the right side of the pier, along Waimea.
Electrical construction for streetlights and communication lines along Haleiwa side has begun.
Construction work for the abutment wall and wing walls along Haleiwa side (left of pier) are still ongoing.
Electrical construction for streetlights and communication lines along Haleiwa side has
begun.
Continued electrical work for the streetlights along Waimea side (right of pier).
Construction for the electrical has begun.
This work is for the streetlights and communication lines.
9 drilled shafts have been successfully completed
9 drilled shafts have been successfully completed to date.


Project waiting for approval to proceed…
Project waiting for approval to proceed with production drilled shafts for the future bridge construction.
Load Test Shaft Concrete Pour Completed
Load Test Shaft concrete pour was completed on 3/17/25. The Load Test Shaft will have to undergo a period of curing time and testing prior to proceeding with the Production Shafts. After completion of the pour for the Load Test, GBI has continued to import fill material and grade for the future road section.
Completion of the Trial Shaft work
The latest update follows the completion of the Trial Shaft work, GBI is working with CMZ to prep and drill the Load Test Shaft, with the concrete pour scheduled for 3/14/25. At the same time, GBI is importing coral fill material to be compacted and placed in the future roadway location. Additionally, the State has recently acquired a parcel that allows work to commence in the Waimea side of the project. GBI went ahead and cleared the area, placed protective barriers and erosion control measures in preparation for grading work.
March 2025
The latest progress update focuses on the commencement of Trial Shaft work. We are collaborating with CMZ to prepare the drill pad area and stage the necessary tools and equipment. CMZ has already completed partial drilling to facilitate the installation of the casings. Concrete placement for the trial shaft is scheduled for Wednesday, 2/26/25.