Work Progress

Blind Renaissance Blind Renaissance

Backfilling of the Abutments

Backfilling of the abutments and wingwalls has commenced using CLSM delivered by our volumetric mixer truck.

Read More
Blind Renaissance Blind Renaissance

Placing dumped riprap for the bridge structures.

Placing dumped riprap for the bridge structures. Dumped riprap placement is currently underway for the bridge structures (see attached photos).

Precast planks are also in production, with the final casting anticipated for mid-December.

Bridge deck activities are expected to begin in mid-January 2026.

Read More
Blind Renaissance Blind Renaissance

Concrete Poured for Abutment #2

Concrete was poured for Abutment #2, more wingwall shaft caps, and the center pier shaft beam.

Read More
Blind Renaissance Blind Renaissance

Concrete Poured for Abutment Wall and Wingwall Shaft Caps, Left Side of Pier

Concrete was poured for the abutment wall and wingwall shaft caps along the left side of the pier.

Read More
Blind Renaissance Blind Renaissance

Haleiwa and Waimea Construction Continuing

Construction for the abutment walls and wing walls along both Haleiwa and Waimea side of the pier is continuing.

Read More
Blind Renaissance Blind Renaissance

Abutment Walls and Wing Walls Ongoing

Construction work for the abutment walls and wing walls along Haleiwa side and Waimea side of the pier is ongoing.

Read More
Blind Renaissance Blind Renaissance

Bridge abutments and wingwalls

Bridge abutments and wingwalls are still currently under construction, with a focus on the left side of the pier.

Read More
Blind Renaissance Blind Renaissance

Electrical installation

Electrical installation work is currently in progress.

Read More
Blind Renaissance Blind Renaissance

Abutment wall and wing walls on left side of the pier, along Haleiwa moves forward.

Construction of abutment wall and wing walls on left side of the pier, along Haleiwa is moving forward.

Read More
Blind Renaissance Blind Renaissance

Abutment wall and wing walls on the right side of the pier, along Waimea begins.

Construction began for the abutment wall and wing walls on the right side of the pier, along Waimea.

Read More
Blind Renaissance Blind Renaissance

Electrical construction for streetlights and communication lines along Haleiwa side has begun.

  • Construction work for the abutment wall and wing walls along Haleiwa side (left of pier) are still ongoing.

  • Electrical construction for streetlights and communication lines along Haleiwa side has

    begun.

  • Continued electrical work for the streetlights along Waimea side (right of pier).

Read More
Blind Renaissance Blind Renaissance

Construction for the electrical has begun.

This work is for the streetlights and communication lines.

Read More