May
Approach slabs are scheduled to be poured second week on May
Following up on our May 1 update, the project remains right on schedule. The approach slabs were successfully poured last week as planned (see attached photos for reference).
Upcoming Schedule:
Stripping approach slab forms
Erecting forms and placing rebar for the end posts
Pouring the end posts
Stripping forms for the end posts