November 2025
Dumped riprap placement is currently underway for the bridge structures (see attached photos).
Precast planks are also in production, with the final casting anticipated for mid-December.
Bridge deck activities are expected to begin in mid-January 2026.
Grading work and riprap placement within the stream bed have been completed.