• Substantial Completion – March 2028

  • Project Completion – May 2028

Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

March 2025

Load Test Shaft in progress, Import Fill commencing simultaneously.

Read More
announcements, schedule Blind Renaissance announcements, schedule Blind Renaissance

February 2025

Begin Bridge Construction Phase 1, Sequence 1, Drilled Shafts

Read More
announcements, schedule Blind Renaissance announcements, schedule Blind Renaissance

January 2025

Clearing and Grubbing, Parking Rearrangement, & Staging Area setup Completed

Read More
announcements, schedule Blind Renaissance announcements, schedule Blind Renaissance

December 2024

BMP measures, and K-Rails Completed

Read More