Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

May 2025

Drilled Shaft Production Began Monday 5/5 on Haleiwa Side of Project.. Five drilled shafts have been successfully completed

Read More
Blind Renaissance Blind Renaissance

May 2025

Project waiting for approval to proceed with production drilled shafts for the future bridge construction.

Read More
Blind Renaissance Blind Renaissance

April 2025

Load Test Shaft concrete pour was completed on 3/17/25

Coral Import is complete.

Read More
Blind Renaissance Blind Renaissance

March 2025

Load Test Shaft in progress, Import Fill commencing simultaneously.

Read More