Estimated Project Milestones Start Bridge Construction - February 2025 Substantial Completion - June 2026 Project Schedule Blind Renaissance 10/6/25 Blind Renaissance 10/6/25 October 2025 Preparing to pour Wingwall #2, Wingwall #4 and Pier Wall. Read More Blind Renaissance 9/4/25 Blind Renaissance 9/4/25 September 2025 Construction for center of pier begins. Read More Blind Renaissance 8/4/25 Blind Renaissance 8/4/25 August 2025 Work for abutment and wingwall on the right side of the pier, going towards Waimea just started. Read More Blind Renaissance 7/16/25 Blind Renaissance 7/16/25 July 2025 Construction began for the abutment wall and wing walls on the right side of the pier, along Waimea. Construction of abutment wall and wing walls on left side of the pier, along Haleiwa moves forward. Read More Newer Posts Older Posts
Blind Renaissance 10/6/25 Blind Renaissance 10/6/25 October 2025 Preparing to pour Wingwall #2, Wingwall #4 and Pier Wall. Read More
Blind Renaissance 9/4/25 Blind Renaissance 9/4/25 September 2025 Construction for center of pier begins. Read More
Blind Renaissance 8/4/25 Blind Renaissance 8/4/25 August 2025 Work for abutment and wingwall on the right side of the pier, going towards Waimea just started. Read More
Blind Renaissance 7/16/25 Blind Renaissance 7/16/25 July 2025 Construction began for the abutment wall and wing walls on the right side of the pier, along Waimea. Construction of abutment wall and wing walls on left side of the pier, along Haleiwa moves forward. Read More