Work Progress Substantial Completion – March 2028Project Completion – May 2028 Blind Renaissance 10/6/25 Blind Renaissance 10/6/25 Concrete Poured for Abutment #2 Read More Blind Renaissance 9/17/25 Blind Renaissance 9/17/25 Concrete Poured for Abutment Wall and Wingwall Shaft Caps, Left Side of Pier Read More Blind Renaissance 9/15/25 Blind Renaissance 9/15/25 Construction of abutment and wingwalls along right side of pier is still ongoing Read More Blind Renaissance 9/4/25 Blind Renaissance 9/4/25 Haleiwa and Waimea Construction Continuing Read More Blind Renaissance 8/16/25 Blind Renaissance 8/16/25 Abutment Walls and Wing Walls Ongoing Read More Blind Renaissance 8/4/25 Blind Renaissance 8/4/25 Bridge abutments and wingwalls Read More Blind Renaissance 7/16/25 Blind Renaissance 7/16/25 Electrical installation Read More Blind Renaissance 7/16/25 Blind Renaissance 7/16/25 Abutment wall and wing walls on left side of the pier, along Haleiwa moves forward. Read More Blind Renaissance 7/16/25 Blind Renaissance 7/16/25 Abutment wall and wing walls on the right side of the pier, along Waimea begins. Read More Blind Renaissance 7/8/25 Blind Renaissance 7/8/25 Electrical construction for streetlights and communication lines along Haleiwa side has begun. Read More Blind Renaissance 7/8/25 Blind Renaissance 7/8/25 Drilled Shaft completed Read More Blind Renaissance 6/17/25 Blind Renaissance 6/17/25 Construction for the electrical has begun. Read More Blind Renaissance 6/17/25 Blind Renaissance 6/17/25 Construction started on abutment and wing walls along Haleiwa side (left of pier). Read More Blind Renaissance 6/3/25 Blind Renaissance 6/3/25 9 drilled shafts have been successfully completed Read More Blind Renaissance 5/16/25 Blind Renaissance 5/16/25 Five drilled shafts have been successfully completed Read More Blind Renaissance 5/6/25 Blind Renaissance 5/6/25 Project waiting for approval to proceed… Read More Blind Renaissance 4/17/25 Blind Renaissance 4/17/25 Coral Import Read More Blind Renaissance 4/2/25 Blind Renaissance 4/2/25 Load Test Shaft Concrete Pour Completed Read More Blind Renaissance 3/13/25 Blind Renaissance 3/13/25 Completion of the Trial Shaft work Read More Progress Blind Renaissance 5/28/19 Progress Blind Renaissance 5/28/19 March 2025 Read More Newer Posts
Blind Renaissance 9/17/25 Blind Renaissance 9/17/25 Concrete Poured for Abutment Wall and Wingwall Shaft Caps, Left Side of Pier Read More
Blind Renaissance 9/15/25 Blind Renaissance 9/15/25 Construction of abutment and wingwalls along right side of pier is still ongoing Read More
Blind Renaissance 9/4/25 Blind Renaissance 9/4/25 Haleiwa and Waimea Construction Continuing Read More
Blind Renaissance 7/16/25 Blind Renaissance 7/16/25 Abutment wall and wing walls on left side of the pier, along Haleiwa moves forward. Read More
Blind Renaissance 7/16/25 Blind Renaissance 7/16/25 Abutment wall and wing walls on the right side of the pier, along Waimea begins. Read More
Blind Renaissance 7/8/25 Blind Renaissance 7/8/25 Electrical construction for streetlights and communication lines along Haleiwa side has begun. Read More
Blind Renaissance 6/17/25 Blind Renaissance 6/17/25 Construction for the electrical has begun. Read More
Blind Renaissance 6/17/25 Blind Renaissance 6/17/25 Construction started on abutment and wing walls along Haleiwa side (left of pier). Read More
Blind Renaissance 6/3/25 Blind Renaissance 6/3/25 9 drilled shafts have been successfully completed Read More
Blind Renaissance 5/16/25 Blind Renaissance 5/16/25 Five drilled shafts have been successfully completed Read More