Estimated Project Milestones


Start Bridge Construction - February 2025


Substantial Completion - June 2026

Project Schedule


Blind Renaissance Blind Renaissance

November 2025

Dumped riprap placement is currently underway for the bridge structures (see attached photos).

Precast planks are also in production, with the final casting anticipated for mid-December.

Bridge deck activities are expected to begin in mid-January 2026.

Grading work and riprap placement within the stream bed have been completed.

Read More
Blind Renaissance Blind Renaissance

October 2025

Preparing to pour Wingwall #2, Wingwall #4 and Pier Wall.

Read More
Blind Renaissance Blind Renaissance

September 2025

Construction for center of pier begins.

Read More
Blind Renaissance Blind Renaissance

August 2025

Work for abutment and wingwall on the right side of the pier, going towards Waimea just started.

Read More